Smart meter obligation 2026: who gets one, what it costs, what a dynamic tariff delivers
Above 6,000 kWh a year a smart meter is mandatory, below that it costs at most 30 euros a year. A dynamic tariff pays off only with load shifting.
The short answer
An intelligent metering system – the smart meter – is mandatory in Germany as soon as a metering point consumes more than 6,000 kilowatt hours of electricity a year, a controllable heat pump or wallbox under § 14a EnWG is connected, or a generation plant above 7 kilowatts is in operation. What it may cost is written into the law: for a voluntary installation in an ordinary household at most 30 euros gross a year, in mandatory cases 40 to 140 euros depending on consumption.
The smart meter does not lower any bill on its own. It is the prerequisite for two things that can: the grid-fee discount under § 14a EnWG and a dynamic electricity tariff, which every supplier has had to offer since 2025. How the 2026 electricity price is made up and which part of it is movable at all is covered in the hub article; this one is about the meter, the costs and the tariff.
Who has to get a smart meter – and who may refuse?
The Metering Point Operation Act (Messstellenbetriebsgesetz, MsbG) distinguishes two devices. The modern metering device (moderne Messeinrichtung) is a digital meter without a communication unit; everyone gets one by the end of 2032, and new buildings and major renovations on completion (§ 29(3) MsbG). The intelligent metering system adds a smart meter gateway that transmits quarter-hourly values.
| Case | Equipment | Basis |
|---|---|---|
| annual consumption above 6,000 kWh | intelligent metering system, mandatory | § 29(1) no. 1 MsbG |
| agreement under § 14a EnWG (heat pump, wallbox) | intelligent metering system plus control device, mandatory | § 29(1) no. 2a MsbG |
| generation plant above 7 kW | intelligent metering system plus control device, mandatory | § 29(1) no. 2b MsbG |
| all other metering points | modern metering device by 31 December 2032; smart meter optional | § 29(2) and (3) MsbG |
What counts is the average of the last three annual consumption values at the metering point, not the current occupant (§ 30(4) MsbG). Anyone moving in therefore inherits the predecessor’s classification until the metering point operator adjusts the value in its annual review.
Nobody can refuse the installation: neither tenants nor owners may prevent or reverse it (§ 36(3) MsbG). The default metering point operator must, however, give at least three months’ notice and point out that a different metering point operator may be chosen (§ 37(2) MsbG). A landlord may choose for the whole property if they equip all electricity metering points with smart meters, bundle at least one further division such as gas or heat via the gateway, and do so at no extra cost compared with separate metering (Bundesnetzagentur, consumer portal).
What may a smart meter cost?
Since 1 January 2025, price caps apply which the legislator raised with the amendment of 25 February 2025. They are split into a share borne by the grid operator and a share that may be charged to the connection user – that is, the electricity customer (§ 30(1) and (3) MsbG, gross per year):
| Consumption group | total | of which connection user |
|---|---|---|
| below 6,000 kWh, optional installation | €60 | €30 |
| 6,000 to 10,000 kWh | €120 | €40 |
| 10,000 to 20,000 kWh, § 14a agreement, plant 7 to 15 kW | €130 | €50 |
| 20,000 to 50,000 kWh, plant 15 to 25 kW | €190 | €110 |
| 50,000 to 100,000 kWh, plant 25 to 100 kW | €220 | €140 |
| above 100,000 kWh, plant above 100 kW | reasonable fee | remainder after deducting the €80 grid operator share |
For the control device at the grid connection, up to 50 euros a year each may additionally be charged to the connection owner and to the grid operator (§ 30(2) MsbG). Anyone requesting early installation pays a one-off charge of up to 100 euros and, in optional cases, up to 30 euros a year extra (§ 35(1) MsbG). Several cases at one metering point are not added together (§ 30(5) MsbG).
One item is not capped: if the meter cabinet has to be converted, the connection owner – the owner or landlord – generally bears the cost, because they are responsible for the electrical installation behind the grid connection (Bundesnetzagentur, consumer portal). In older apartment buildings that is the real cost item – not the meter.
How far has the roll-out got – and which deadlines apply?
As at 30 June 2026, metering point operators reported 54,135,202 metering locations, of which 3,172,579 had an intelligent metering system installed – 5.9 per cent (Bundesnetzagentur, press release of 21 September 2026). Since March 2026 the regulator has opened supervisory proceedings against 434 companies that missed the 20 per cent quota; at 77 of them the quota was zero.
The law will in future measure progress in period quotas (§ 45(1) MsbG): by the end of 2025, 20 per cent of all mandatory cases up to 100,000 kilowatt hours had to be equipped, in each period to 2026, 2028 and 2030 90 per cent of the metering points newly due, and by the end of 2032 90 per cent of all mandatory cases. For large consumers above 100,000 kilowatt hours the obligation only starts in 2028. So the letter from the metering point operator is certain to come; only the timing is open.
What does a dynamic electricity tariff deliver?
Since 1 January 2025 every electricity supplier has had to offer customers with an intelligent metering system a contract with a dynamic tariff (§ 41a(2) EnWG); suppliers with more than 200,000 customers must also keep a fixed-price contract with at least twelve months’ price guarantee on offer (§ 41a(4) EnWG). Before signing, customers must be informed about costs, advantages and risks (§ 41a(6) and (7) EnWG).
The dynamic tariff passes through the previous day’s exchange price hour by hour, plus grid fees, levies, taxes and a standing charge. What that means is shown by autumn 2026: in October the day-ahead price averaged 169.27 euros per megawatt hour over the month, that is 16.9 cents per kilowatt hour (SMARD). On 10 November, during the “Dunkelflaute” of low wind and sun, the daily average was above 35 cents. For comparison: in the BDEW electricity price analysis of autumn 2026, procurement and sales account for 15.2 cents per kilowatt hour of a household tariff.
So anyone who simply carried on consuming as usual in October 2026 did not save with the dynamic tariff but paid the monthly average. The advantage arises exclusively from shifting: a heat pump with a buffer tank, an electric car charging at night, a battery store in a business – they buy in the hours when wind and sun push the price down and avoid the evening peak. Without controllable load, the dynamic tariff is a bet on the weather.
Worked example: apartment building with a central heat pump
Assumptions: apartment building with ten flats, central heat pump using 25,000 kilowatt hours of electricity a year with a § 14a agreement, common-area electricity 4,000 kilowatt hours, flats 2,500 kilowatt hours each (freely chosen figures; price caps under § 30 and § 35 MsbG, as of 16 November 2026).
| Metering point | Classification | at most per year | who pays |
|---|---|---|---|
| heat pump 25,000 kWh, § 14a | mandatory, group 20,000–50,000 kWh | €110 metering + €50 control device | connection user (metering), connection owner (control) |
| common-area electricity 4,000 kWh | optional | €30 | owner, recoverable as metering operating costs |
| 10 flats at 2,500 kWh each | optional | €30 each, one-off €100 if requested early | tenants as connection users |
For the owner that is 160 euros a year for the heat pump in the mandatory case, and for the tenants 30 euros each if the metering point operator opts for the optional installation. Against that stands the § 14a discount: in the example network of the § 14a article, a good 120 euros flat rate or 60 per cent off the grid-fee energy charge – at 25,000 kilowatt hours considerably more than the meter costs. So here the smart meter pays off not through the tariff but through the grid fee. The dynamic tariff only comes on top once the heat pump with buffer tank is actually shifted into the cheap hours.
What owners, landlords and businesses should do now
- Read the three-year average of each metering point from the bills and check whether it is above 6,000 kilowatt hours – the obligation and the price group hinge on that.
- Check the metering point operator’s invoices against the table in § 30 MsbG; more than the cap may not be charged, not even as the sum of several cases.
- For a heat pump or wallbox, plan the § 14a agreement together with the smart meter; that is where the certain benefit lies.
- As a landlord, check whether bundling electricity and heat via one gateway makes sense for the whole property – and have the meter cabinet inspected by an electrician first.
- Sign a dynamic tariff only if a controllable load exists; otherwise choose the fixed-price contract under § 41a(4) EnWG and just watch the hourly prices for a year.
- As a business above 100,000 kilowatt hours, note the 2028 start of the obligation and use the load profiles from interval metering for tariff selection until then.
FAQ
Who has to get a smart meter in Germany?
An intelligent metering system is mandatory for an annual electricity consumption above 6,000 kilowatt hours, for an agreement under § 14a EnWG (controllable heat pump or wallbox) and for generation plants above 7 kilowatts (§ 29(1) MsbG). Everyone else receives at least a modern digital meter by the end of 2032; the metering point operator may also fit a smart meter voluntarily.
What does a smart meter cost per year?
The law caps the price by consumption: for a voluntary installation below 6,000 kWh the connection user pays at most 30 euros gross a year, for 6,000 to 10,000 kWh 40 euros, up to 20,000 kWh or with a § 14a agreement 50 euros, up to 50,000 kWh 110 euros, up to 100,000 kWh 140 euros (§ 30 MsbG, since 1 January 2025). For a control device, up to 50 euros more may be charged to the connection owner.
Can I refuse the installation of a smart meter?
No. Neither the connection user nor the connection owner may prevent or reverse the installation (§ 36(3) MsbG). The metering point operator must, however, give three months’ notice and point out the free choice of another metering point operator (§ 37(2) MsbG).
Is a dynamic electricity tariff worth it?
Only with load shifting. A dynamic tariff passes the exchange price through hour by hour: in October 2026 the day-ahead price averaged 16.9 cents per kilowatt hour over the month, and on 10 November the daily average was above 35 cents. Those who can move heat pump, storage or charging into cheap hours benefit; those who cannot control their load carry the price risk.
Sources
- § 29 MsbG: Ausstattung von Messstellen mit intelligenten Messsystemen (Pflichteinbau ab 6.000 kWh, § 14a, Anlagen über 7 kW), gesetze-im-internet.de (abgerufen 16.11.2026)
- § 30 MsbG: Preisobergrenzen für intelligente Messsysteme und Steuerungseinrichtungen ab 01.01.2025, gesetze-im-internet.de (abgerufen 16.11.2026)
- § 45 MsbG: Ausstattungsverpflichtungen und Zeitraumquoten bis 2032, gesetze-im-internet.de (abgerufen 16.11.2026)
- § 41a EnWG: Dynamische Stromtarife (Angebotspflicht seit 01.01.2025) und Festpreisverträge, gesetze-im-internet.de (abgerufen 16.11.2026)
- Bundesnetzagentur: Pressemitteilung „Bundesnetzagentur veröffentlicht halbjährliche Erhebung im Messwesen“ vom 21.09.2026 (Stichtag 30.06.2026: 3.172.579 intelligente Messsysteme, 5,9 Prozent)
- Bundesnetzagentur / SMARD: Großhandelspreis Day-Ahead DE-LU, Monatswerte (Oktober 2026: 169,27 €/MWh; abgerufen 10.11.2026)
Editorial note: researched and drafted with AI support; selection, analysis and quote are reviewed and owned by Pedram Dadgar. Corrections are marked with a date. How we work